4. Lampiran 2A

download 4. Lampiran 2A

of 13

Transcript of 4. Lampiran 2A

  • 8/6/2019 4. Lampiran 2A

    1/13

    10

    Lampiran 2A

    TENAGA NASIONAL BERHADSENARAI SEMAK TERPERINCI KEBENARAN MERANCANG

    BIL PERKARA-PERKARA YANG DISEMAKSELARAS KEPERLUANJABATAN/AGENSI

    ADA/TIADA CATATAN

    Bil Dokumen1 Keperluan penyediaan pencawang

    elektrik mengikut jenis bangunandengan keluasan minima bangunanyang ditetapkan serta keluasankawasan berpagar mengikutkeperluan. Segala set back bagibangunan perlu mematuhi syarat-syarat yang ditetapkan oleh PihakBerkuasa Tempatan dan mana-

    mana agensi kerajaan yangberkaitan.

    To provide a substation inaccordance to the type of buildingwith a specified minimum areaincluding its gated compound. Allsetbacks for the building shallcomply with the requirements of theLocal Authorities and any othergovernment agencies deemednecessary.

    2 Pemaju dikehendaki memastikanJuruperunding Elektriknyamengemukakan lukisan berikutkepada TNB untuk kelulusan pelanbangunan pencawang sebelumpembinaan bermula:

    a. 3 salinan lukisan lengkap rekabangunan pencawang pelanarkitek dan pelan struktur RCbangunan yang diperaku olehJurutera Struktur yang bertauliah.

    b. 3 salinan pelan lokasipembangunan.c. 12 salinan pelan Pre-Computationdan surat hakmilik tanah bagi tapakpencawang.

    Prior to commencement ofconstruction Developer must ensureits Electrical Consultant submits the

  • 8/6/2019 4. Lampiran 2A

    2/13

    11

    BIL PERKARA-PERKARA YANG DISEMAKSELARAS KEPERLUANJABATAN/AGENSI

    ADA/TIADA CATATAN

    relevant drawings for TNBsapproval on the substation buildingplan:

    a. 3 sets of complete drawings ofsubstation Architectural & RCStructural Drawings duly signed orendorsed by Structural Engineer.b. 3 sets of Site Location Plan withrespect to development.c. 12 sets of Pre-Computation planor Land Title copies for substationland.

    3 Senarai Semak Ulasan Permohonan

    Pelan Pembangunan - TenagaNasional Berhad (TNB)

    No Rujukan :Tarikh :Tajuk Permohonan KebenaranMerancang

    Senarai Semak Utama

    1. Pelan Susun Atur (4 salinan)2. Pelan Lokasi (4 salinan)

    3. Pelan Kunci (4 salinan)4. Pelan Kontur (4 salinan)5. Anggaran Beban Permulaan &Beban Muktamad (1 salinan)

    Maklumat Tambahan YangDiperlukan :

    6. Beban Keseluruhan : _______kW7. Keluasan Tanah : _______ ekar8. Keluasan lantai : _______ m2

    9. Laluan kabel / talian atas TNB

    a) Laluan kabel bawah tanah : Perlu/ Tidak Diperlukan

    Cadangan Right Of Way (ROW)sekiranya laluan kabel bawah tanahdiperlukan dan ianya hendaklahberdasarkan kepadaketetapan

  • 8/6/2019 4. Lampiran 2A

    3/13

    12

    BIL PERKARA-PERKARA YANG DISEMAKSELARAS KEPERLUANJABATAN/AGENSI

    ADA/TIADA CATATAN

    TNB.

    b) Laluan talian atas :Perlu / Tidak Diperlukan

    Cadangan Right Of Way (ROW)sekiranya laluan talian ataspenghantaran diperlukan

    40 meter : Satu talian atas 60 meter : Dua talian atas 80 meter : Tiga talian atas

    Kedudukan tapak pencawangelektrik hendaklah memenuhi

    perkara-perkara berikut :-10. Tiada terdapat halangan danmempunyai access terus kepadajalan utama.

    11. Pemaju menyediakan accessroad tarmac dari jalan besar ketapak pencawang. Pemaju perlumerujuk kepada TNB bagipengesahan dan kelulusan untukpenyediaan access road tarmac.12. Berada di atas paras banjir, jauh

    daripada loji najis dan tempatpembuangan sampah.13. Paras keseluruhan tapakpencawang berada sama denganparas jalan (platform bukan dalamlurah, lembah atau lereng bukit danbukan di basement)14. Tapak cadangan perlulah bebasdaripada halangan tuntutan undang-undang.15. Senarai nama dan lokasipencawang-pencawang TNB yang

    paling hampir dengan pembangunanyang berkenaan (dilampirkandengan terperinci).16. Menyediakan frontage jalanpencawang mengikut spesifikasiTNB.

    Nota :Tempoh sah laku ulasan adalah 2

  • 8/6/2019 4. Lampiran 2A

    4/13

    13

    BIL PERKARA-PERKARA YANG DISEMAKSELARAS KEPERLUANJABATAN/AGENSI

    ADA/TIADA CATATAN

    tahun dari tarikh kelulusan.

    Checklist for Comments on theApplication of the Development Plan Tenaga Nasional Berhad (TNB)

    Reference No :Date :Title of Development PlanningApproval :

    Main checklist

    1. Layout Plan (4 copies)2. Location Plan (4 copies)

    3. Key Plan (4 copies)4. Contour Plan (4 copies)5. Estimated Initial & Final Load (1copy)

    Additional Information required :

    6. Total Load : _______kW7. Land Area : ________ acres8. Floor area : ________ m29.TNBs cable / overhead lines route

    a) Underground cable route :Required / Not required

    Proposed Right of Way (ROW) isrequired for underground cable andit shall be in accordance to TNBsrequirements.

    b) Overhead lines route :Required / Not required

    Proposed Right of Way (ROW) is

    required for transmission overheadlines :

    40 metres : Single overhead lines 60 metres : Double overhead lines 80 metres : Triple overhead lines

    Location of the substation shallcomply to the following :

  • 8/6/2019 4. Lampiran 2A

    5/13

    14

    BIL PERKARA-PERKARA YANG DISEMAKSELARAS KEPERLUANJABATAN/AGENSI

    ADA/TIADA CATATAN

    10. No obstruction and must havedirect access to the main road.11. Developer to provide tarmacaccess road from the main road tosubstation site. The readiness of thetarmac access road shall besubjected to TNBs confirmation andapproval.12. Shall be above flood level, awayfrom sewerage plants and rubbishdumping ground.13. Overall substation level shall bethe same with road level (platform not on slopes, valley , hillside andnot in the basement).

    14. Proposed site shall be free fromany legal claims / encumbrances.15. List of names and location ofTNBs substation located nearest tothe development. (attached indetail).16. To provide substation roadfrontage according to TNBspecifications.

    Note:Validity of the comments : 2 years

    from the approval date.

    4 Penyediaan peparit kabel dan tebaldinding pencawang mengikutpiawaian TNB untuk memasangpapan agihan. Peparit konkrit kabelpencawang hendaklah dibinasehingga melepasi kawasan parit diluar pencawang.

    To provide cable trench andthickness of substation wall

    according to TNB Standards for thepurpose of installing the distributionboard. Concrete cable trench mustbe built and extended beyond theexternal drains outside thesubstation.

    5 Pembangunan bangunan ataukompleks bertingkat, bangunanpencawang elektrik hendaklah

  • 8/6/2019 4. Lampiran 2A

    6/13

    15

    BIL PERKARA-PERKARA YANG DISEMAKSELARAS KEPERLUANJABATAN/AGENSI

    ADA/TIADA CATATAN

    berasingan dari bangunan ataukompleks bertingkat.

    For development of building or multi-storey complex, the substationbuilding shall be located separatelyfrom the building or multi-storeycomplex.

    6 Frontage jalan pencawangmengikut ukuran yang ditetapkanoleh PBT perlu disediakan.

    To provide substation road frontageaccording to Local Authorities

    requirements.

    7. Senarai Semak

    1. Jumlah Beban Pengguna > 100kVAa. ________ Pencawang Elektrik(PE) Single Chamber (14.63 m x14.63 m) tidak termasuk land setback)b. ________ PE Double Chamber(17.68 m x 14.63 m) tidak termasuk

    land set back) Beban alatubah tidak melebihi 60% Jika beban keseluruhan melebihi100kVA keperluan pencawangelektrik adalah mandatori.

    2. Jumlah Beban Pengguna : 5 MVAsehingga 25 MVAa. ______ PencawangPembahagian Utama jenis indoor(PPU) (46 m x 46 m tidak termasukland set back).

    b. ________ PPU jenis outdoor (130m x 130 m tidak termasuk land setback) Jika beban keseluruhan melebihi5MVA (5000kVA) keperluan PPUadalah mandatori.

    3. Jumlah Beban Pengguna > 5MVA(khusus untuk 1 pengguna seperti

  • 8/6/2019 4. Lampiran 2A

    7/13

    16

    BIL PERKARA-PERKARA YANG DISEMAKSELARAS KEPERLUANJABATAN/AGENSI

    ADA/TIADA CATATAN

    kilang atau pengguna bekalan pukal33kV)a. ______ Stesen Suis Utama (SSU)33kV jenis conventional (31 m x 31m tidak termasuk land set back)

    4. Jumlah Beban Pengguna : 1MVA (1000 kVA) hingga 5MVA(5000 kVA) (khusus untuk 1pengguna seperti kilang ataupengguna pukal 11kV)a. _______ SSU 11kV jenisconventional (31 m x 31 m tidaktermasuk land set back)

    5. Jumlah Beban Pengguna >25MVA (25000 kVA)a. _________ Pencawang MasukUtama (PMU) 132kV air insulatedswitchgear with outdoor switchyard(122 m x 122 m tidak termasuk landset back)b. _______ SSU 132kV jenisconventional ( _m x _m tidaktermasuk land set back)c. ___________ PMU 275kV (305 mx 305 m).

    Checklist

    1. Total Connected Load > 100kVAa. ________ Single ChamberDistribution Substation (PE) (14.63m x 14.63 m not including land setback)b. ________ Double ChamberDistribution Substation (PE) (17.68m x 14.63 m not including land set

    back) Transformer load not exceeding60%. If total load exceeds 100kVA,provision of DistributionSubstation(s) (PE) is mandatory.

    2. Total Connected Load : 5 MVA to25 MVA

  • 8/6/2019 4. Lampiran 2A

    8/13

    17

    BIL PERKARA-PERKARA YANG DISEMAKSELARAS KEPERLUANJABATAN/AGENSI

    ADA/TIADA CATATAN

    a.________ Main DistributionSubstation indoor type (PPU) (46 mx 46 m not including land set back)b. ________ Main DistributionSubstation outdoor type (PPU) (130m x 130 m not including land setback) If total load exceeds 5MVA(5000kVA), provision of MainDistribution Substation (PPU) ismandatory.

    3. Total Connected Load > 5 MVA(specifically for one (1) customere.g. factory or 33kV bulk supply

    customer)a. ________ 33kV Main SwitchingStation conventional (SSU) (31 m x31 m not including land set back)

    4. Total Connected load of 1 MVA(1000 kVA) to 5MVA (5000 kVA)(specifically for one (1) customere.g. factory or 11kV bulk supplycustomer)a. ________ 11kV Main SwitchingSubstation conventional (SSU) (31

    m x 31 m not including land setback)

    5. Total Connected Load > 25MVA(25000 kVA)a. ________ 132kV TransmissionMain Intake air insulated switchgearwith outdoor switchyard (PMU)b. ________ 132kV Main SwitchingSubstation conventional (SSU)c. __________ 275kV TransmissionMain Intake (PMU) (305m x 305m)

    8. Sebarang paip serbis ataupepasangan pihak pengguna tidakdibenarkan melalui di dalampencawang elektrik kecualidiperlukan TNB.

    Any service pipes or installation byconsumer shall not pass through the

  • 8/6/2019 4. Lampiran 2A

    9/13

    18

    BIL PERKARA-PERKARA YANG DISEMAKSELARAS KEPERLUANJABATAN/AGENSI

    ADA/TIADA CATATAN

    substation unless otherwisespecified by TNB.

    9. Kedudukan papan suis utamapengguna hendaklah bersebelahandengan bilik pencawang alatubahTNB, dengan jarak maksima tidakmelebihi 25 meter.

    The location of the customer mainswitchboard shall be next to the TNBtransformer room, with a maximumdistance not exceeding 25 metres.

    10 Bagi bilik papan suis utama,

    sekiranya pemasangan papan suisutama dari jenis floor mounted /pedestal jarak sekeliling papan suisutama dari dinding bilik mestilahtidak kurang daripada 3 kaki.

    For the main switchboard room, ifinstallation of the main switchboardis of a floor mounted / pedestal type,the radial distance of the mainswitchboard from the substationwalls shall not be less than 3 feet.

    11 Syarat-syarat yang dikenakanhanyalah untuk permohonanbekalan di pembangunan ini sahaja.Sekiranya pembangunan masahadapan dijalankan secaraberperingkat, TNB akanmengenakan syarat-syaratberpandukan perancangan sistemsecara menyeluruh pembangunandengan mengambil kirapembangunan sedia ada yang telah

    siap.

    he conditions imposed areapplicable to supply application forthis particular development only.Should the future development becarried out in stages, TNB shallhave the right to impose additionalconditions based on the overall

  • 8/6/2019 4. Lampiran 2A

    10/13

    19

    BIL PERKARA-PERKARA YANG DISEMAKSELARAS KEPERLUANJABATAN/AGENSI

    ADA/TIADA CATATAN

    system planning, taking intoconsideration the current completeddevelopment.

    12 Sebarang pepasangan TNB sediaada seperti tiang sesalur atas,menara talian, kabel bawah tanahdan pencawang elektrik yangdiminta oleh pemaju untukdikeluarkan dari tapakpembangunan sebelum pembinaanbermula akan ditanggung kos penuhpengubahannya oleh pemaju.

    Any existing TNBs installation such

    as overhead poles, towers,underground cables and substationrequested by the developer to beremoved from the development sitebefore commencement ofconstruction, the full cost forrelocation shall be borne by thedeveloper.

    13 Pemaju dikehendaki membekaltiang-tiang lampu jenis yangdiluluskan atau tiang konkrit yang

    piawai seperti disyaratkan olehMajlis Tempatan, dan dipasang dilokasi mengikut kelulusan MajlisTempatan yang terlibat.

    Developer is required to supplyapproved streetlighting poles orstandard concrete poles as imposedby Local Authorities and shall installat the locations approved by therelevant Local Authorities.

    14 Segala kos tambahan yangdikenakan seperti Route Mapping &Microtunelling yang disyaratkanoleh Majlis Tempatan dan lain-lainJabatan Berkuasa Kerajaan akanditanggung oleh pihak pengguna /pemaju.

    All additional cost incurred for

  • 8/6/2019 4. Lampiran 2A

    11/13

    20

    BIL PERKARA-PERKARA YANG DISEMAKSELARAS KEPERLUANJABATAN/AGENSI

    ADA/TIADA CATATAN

    conditions imposed by LocalAuthorities and other relevantGovernment Authorities such asRoute Mapping & Microtunnellingworks, shall be borne by theconsumer / developer.

    15 Bekalan elektrik hanya diberi setelahpencawang elektrik dimulatugaskandan kebenaran merentang kabelbawah tanah di kawasan berkenaandiperolehi daripada Jabatan-JabatanBerkuasa Kerajaan. Bayaran cassambungan pengguna akandikenakan bagi bekalan ke premis

    berkenaan dan mestilah dijelaskansebelum kerja tapak dimulakan.

    Electricity supply will only be givenupon commissioning of thesubstation and after obtaining theapproval to lay underground cablesfrom the respective GovernmentAuthorities. Consumer ConnectionCharges shall be imposed for supplyof electricity to the said premise andthe charges shall be paid in full

    before commencement of site works

    16 Pihak TNB berhak memasuki kedalam kawasan pencawang padabila-bila masa selepas ianyadimulatugaskan atau diambilaliholeh TNB.

    TNB shall have the right to enter thesubstation area at any given timeafter commissioning or handing overof the substation to TNB.

    17 Pihak tuan punya bangunan danpengurusan bangunan, MESTILAHmembenarkan pihak TNBmerentang kabel-kabel bawah tanahpada bila-bila masa sama ada keatau dari pencawang berkenaan.Tiada sebarang syarat bolehdikenakan ke atas TNB.

  • 8/6/2019 4. Lampiran 2A

    12/13

    21

    BIL PERKARA-PERKARA YANG DISEMAKSELARAS KEPERLUANJABATAN/AGENSI

    ADA/TIADA CATATAN

    Building owners and buildingmanagement shall allow TNB at anytime to lay underground cables to orfrom the substation. No conditionsshall be imposed on TNB.

    18 Pihak TNB juga berhak mengambilbekalan daripada pencawang yangberkenaan untuk kegunaan di luarkawasan pembangunan / kilangpada bila-bila masa di masahadapan.NB shall have the right to takesupply from the said substation for

    the usage outside the developmentarea / factory at any given time inthe future.

    19 Sebarang perubahan danpembaharuan pelan tersebut di atashendaklah dihantar ke pejabat TNBuntuk diproses semula.

    Any changes and modification of theplan above shall be sent to TNBsoffice to be re-processed.

    20 Pihak pemaju bertanggungjawabsepenuhnya dan menanggung kossekiranya apa-apa pengalihanperubahan tiang / peti pembekalhendak dijalankan di masa depanselepas kerja-kerja TNB dibuat.

    Developer is fully responsible andshall bear all costs for any futurerelocation of poles / feeder pillarsafter completion of TNBs work.

    21 Pihak pemaju bertanggungjawabuntuk menjaga pepasangan TNBsehingga mendapat 'Certificate ofCompletion and Compliance' (CCC).Segala kehilangan dan kerosakansebelum mendapat CCC adalahmenjadi tanggungjawab pemajuuntuk membayar kos penggantian

  • 8/6/2019 4. Lampiran 2A

    13/13

    22

    BIL PERKARA-PERKARA YANG DISEMAKSELARAS KEPERLUANJABATAN/AGENSI

    ADA/TIADA CATATAN

    dan pembaikan tersebut.

    The developer shall be responsiblefor the security of TNBs installationuntil the Certificate of Completionand Compliance (CCC) is obtained.Any loss and damages beforeissuance of CCC shall be theresponsibility of the developer. Allreplacement and repair costs shallbe borne by the developer.

    22 Pihak pemaju perlu mematuhisemua spesifikasi dan keperluanTNB.

    Developer is required to comply toall TNB specifications andrequirements.

    23 Sebarang rezab/rentis talian danpepasangan TNB sediada/dalampelaksanaan di dalam kawasanpembangunan perlu dikekalkan.Tiada sebarang pembangunanboleh dilaksanakan di atas tanahyang melibatkan rentis dan

    pepasangan TNB. Semuaperancangan pembangunanhendaklah di luar kawasan rentisdan pepasangan TNB.

    Any reserve/wayleave area for TNBlines and installations(existing/under construction) withinthe development area must bemaintained. No other developmentshould take place on land markedfor TNB wayleave or with existing

    TNB installations. All planning fordevelopment must be outside TNBwayleave and installations area.