Matrik Plan Overburden (Jarak Tambang - Disposal + 1000 meter) I. Excavator PC-200
a.
Kapasitas Bucket = 0,9
Lcm
b.
Bucket Faktor = 0,85
c. Cycle Time = 20
detik
d.
Effisiensi Kerja = 0,78
Kapasitas Produksi = 107,41
Lcm/jam
= 88,39514
Bcm/jam
Dump Truck
a.
Kapasitas Vessel = 9
Lcm
b.
Kapasitas Bucket = 0,9
Lcm
c.
Bucket Factor = 0,85
Jumlah Pengisian = 11,1
Bucket
11
Bucket
d.
Waktu muat = 11 x 20
60
= 3,67 menit