1. Rencana Anggaran Biayaa. Biaya Produksi Komponen Modular PracetakUraian PekerjaanSatuanVolume PekerjaanHarga SatuanJumlah

Pembetonan

1. Fondasi f'c 26,4 Mpam30.840859,475.14721,959.12

2. Sloof f'c 26,4 Mpam30.8046859,475.14691,533.70

3. Kolom f'c 26,4 Mpam30.9891859,475.14850,106.86

4. Balok f'c 26,4 Mpam30.8046859,475.14691,533.70

Jumlah2,955,133.38

Tulangan

Tulangan Utama

1. Fondasikg115.589,546.081,103,373.53

2. Sloofkg173.389,546.081,655,060.30

3. Kolomkg200.709,546.081,915,935.44

4. Balokkg173.389,546.081,655,060.30

Jumlah6,329,429.57

Tulangan Begel

1. Sloofkg63.289,546.08604,066.08

2. Kolomkg59.189,546.08564,976.49

3. Balokkg63.289,546.08604,066.08

Jumlah1,773,108.65

Plat Profil

1. Plat Sambungan fondasikg48.0019,346.00928,608.00

2.Plat Sambungan kolom ataskg48.0019,346.00928,608.00

3. Plat sambungan kolom bawahkg14.0019,346.00270,844.00

4. Plat sambungan Kolom ke kolomkg28.0019,346.00541,688.00

Jumlah2,669,748.00

Pemasangan Dinding GRC

1. Dinding GRCm2200.465276,996.3615,435,089.90

Jumlah15,435,089.90

Total29,162,509.50